Go top
Project information

Excom-Siroco Planning: Consideration of renewable assets for SRS service

J. García-González A.F. Oviedo-Gómez

September 2024 - November 2024

Funding entity Endesa Medios y Sistemas S.L


The general objective of the project is to carry out the necessary developments so that the production version of the Excom-Siroco Planning model (ExSp) allows for the consideration of secondary regulation services provision by renewable assets


Layman's summary: This project is part of the developments of the Excom-Siroco Planning model (ExSP), which allows for the operation planning of Endesa's entire generation portfolio in the Iberian Peninsula, considering both the energy market and the secondary regulation reserve market. The modeling of the generation units is done with a high level of detail (thermal units and hydro turbines) and is coordinated with other models developed by the same IIT team (EXCOM and EXLA models). This collaboration includes the possibility of providing regulation capacity through renewable assets.



Techniques employed: Mixed-Integer Linear Programming



2024_EXSP_ActivosRES